About Mactung Project
A 2023 Technical Report announced updated mineral resources for Mactung. The mineral resource totaled 41.5 Mt Indicated Resource at 0.73% WO3and 12.2 Mt Inferred Resource at 0.59% WO3. It is estimated that there is the potential for an Exploration Target at Mactung of between 2.5 and 3.5 Mt at a grade of between 0.4 and 0.6% WO3in addition to the current Mineral Resources disclosed (see Fireweed news release). These results make it the world’s largest high-grade tungsten deposit.*
News releases19 on file
Fireweed Metals Commences 2026 Field Program
A 2026 field program has begun, comprising roughly 9,500 m of combined diamond and sonic drilling, with up to 7,500 m at Macpass and up to 2,000 m at Mactung in Yukon. Drilling is underway at Macpass, including completion of TS25-003, a 450 m down-dip step-out at Tom South, plus ~1,500 m at Tom East and regional gravity and soil surveys. Mactung geotechnical, hydrogeological and baseline work supp
Drill resultsFireweed Metals Commences Mactung Tungsten Project Feasibility Study
An updated Feasibility Study has begun for the 100%-owned Mactung Tungsten Project in Yukon, Canada, with completion targeted for early 2027 to support mine license applications expected to be submitted in 2027. Wood Canada is lead study consultant, with SLR updating the mineral resource estimate using over 11,000 metres of 2025 drilling and roughly 40,000 metres of historical data, alongside Ause
Study resultsFireweed Metals Corp. and Ross River Dena Council Sign Exploration and Collaboration Agreement for Mactung and Macpass Projects
An Exploration and Collaboration Agreement has been signed with the Ross River Dena Council covering the Mactung tungsten and Macpass zinc-lead-silver projects in the Ross River Area of the Kaska Nation Traditional Territory, Yukon. The agreement sets out communication protocols, measures to protect lands, waters and culturally significant sites, direct capacity funding for RRDC participation, and
CorporateFireweed Intersects Zinc Mineralization in 300 m Step Out at Tom South and Provides Macpass Regional Update
Hole TS25-003, a 300 m step-out at Tom South on the Macpass project in Yukon, intersected 58.30 m grading 2.33% zinc, 0.04% lead and 1.79 g/t silver from 1,164 m, including 5.24 m of 7.80% zinc, 0.05% lead and 2.33 g/t silver; the hole was stopped in mineralization at about 1,222 m due to weather and will be resumed in 2026. Regional holes at Oro returned 13.00 m of 0.45 g/t gold, while Goliath an
Drill resultsMactung Project Update
A 11,117 m, 66-hole multi-purpose drill program at the Mactung tungsten project in Yukon has been completed, with assays including 12 m true width of 6.21% WO3 in MT25-048, 16 m of 4.53% WO3 in MT25-051, 29 m of 2.56% WO3 in MT25-034 and 15 m of 2.15% WO3 in MT25-038. A Mineral Resource update and Feasibility Study, funded by the US$15.8 M DPA Title III award, begin before end-2025, with the study
CorporateFireweed Intersects 30 m True Width of 33.2% Zinc Equivalent in 115 m Step-Out at Tom South
Hole TS25-001D1 at the Tom South zone of the Macpass Project, Yukon, returned 30 m true width (54.82 m intersected) grading 33.23% zinc equivalent (18.20% Zn, 13.93% Pb, 161.0 g/t Ag) from 891.6 m downhole, including 7.0 m true width at 59.60% ZnEq, in a 115 m down-dip step-out beyond the 2024 Mineral Resource. At Tom West, infill twin TS25-002D1 cut 83 m true width of 5.75% ZnEq. Mactung drilling
Drill resultsFireweed Signs Funding Agreement with the Government of Canada Valued at $12.9M to Advance Planning for North Canol Road and Power Improvements
A Contribution Agreement with Natural Resources Canada provides $12.9M to fund planning for road and transmission line improvements in the North Canol corridor, the access route to Fireweed's Macmillan Pass projects near the Yukon–NWT border. The funding completes due diligence for the Critical Minerals Infrastructure Fund contribution announced December 13, 2024. Planned improvements include upgr
CorporateFireweed Grants Stock Options
Stock options exercisable into 2,595,000 common shares were granted to certain officers, employees and consultants under the company's stock option plan. The options carry an exercise price of C$1.48 per share and a five-year term. Fireweed is 100% owner of the 985 km2 Macpass District in Northern Canada, which includes the Macpass zinc-lead-silver project and the Mactung tungsten project.
CorporateFireweed Announces $30 Million Financing
A non-brokered private placement for gross proceeds of up to CAD$30,000,000 has been launched, comprising 9,090,909 common shares at CAD$1.10 per share and 11,646,482 premium flow-through common shares issued through a charitable donation arrangement. The Lundin Family Trusts have indicated an intention to subscribe for up to $30.0 million. Proceeds will fund a 14,000-metre drilling and regional e
FinancingFireweed Provides Year-End Review of Record-Setting 2023 Accomplishments
A 2023 year-end review reports over 22,500 m drilled at the Macpass zinc-lead-silver project in Yukon, including hole NB23-007 with 15 m (true width) of 11.9% zinc, 2.2% lead, 81.2 g/t silver and 40 m (true width) of 15.1% zinc, 2.8% lead, 85.8 g/t silver; assays are pending for 26 of 52 holes, with results expected in early 2024. Fireweed also completed the acquisition of 100% of the 37.6 km² Mac
CorporateFireweed Metals Files Technical Report for its Mactung Project on SEDAR
An NI 43-101 technical report for the Mactung tungsten project in Yukon and Northwest Territories, Canada, has been filed on SEDAR, with an effective and report date of July 28, 2023, authored by Garth Kirkham, P.Geo. of Kirkham Geosystems Ltd. Resources total 41.5 Mt Indicated at 0.73% WO3 and 12.2 Mt Inferred at 0.59% WO3, plus an Exploration Target of 2.5 Mt to 3.5 Mt at 0.4% to 0.6% WO3. Resul
Study resultsFireweed to Commence Gold Exploration Program at Macmillan Pass in an Emerging Gold District, Yukon
A three-week, C$250,000 reconnaissance greenfields gold program will begin at the 980 km² Macmillan Pass and Mactung projects in Yukon, involving prospecting, mapping and sampling of gold anomalies targeting reduced intrusion-related gold mineralization, led by Jodie Gibson, P.Geo. The work runs alongside Fireweed's ~C$20M drill program focused on step-out drilling of zinc-lead-silver zones at Tom
Drill resultsFireweed Announces Near-Term Plans for Mactung Project
A Preliminary Economic Assessment on the Mactung tungsten project in Yukon will begin this quarter and conclude before year-end, building on North American Tungsten's 2009 Feasibility Study. A metallurgical test program with Base Metallurgical Laboratories Ltd. to optimize the flowsheet and evaluate gold and copper recovery is underway, with results expected in Q4 2023, alongside summer environmen
CorporateFireweed Metals Announces Mineral Resources for the Mactung Project: the Largest High-Grade Tungsten Deposit in the World*
A new mineral resource estimate for the Mactung tungsten project, straddling the Yukon–Northwest Territories border, totals 41.5 Mt Indicated at 0.73% WO3 and 12.2 Mt Inferred at 0.59% WO3, with an additional Exploration Target of 2.5–3.5 Mt at 0.4–0.6% WO3. Cut-off grades of 0.25% WO3 (open pit) and 0.5% WO3 (underground) were based on a US$240/mtu concentrate price. Copper and gold were estimate
Resource updateFireweed Announces Plans for 16,000m Drill Program at Macmillan Pass and Appoints New Vice President of Operations
At least 16,000 m of drilling with five drills is planned for the 2023 season at the Macmillan Pass zinc-lead-silver project in Yukon, focused on step-out drilling at the Boundary Zone and step-out and infill drilling at the Tom and Jason deposits, with mobilization in May, drilling from June to September and a camp expansion to house up to 150 people. Andrew Crook, P.Eng., previously Deputy Proje
Drill resultsFireweed Announces Signing of Definitive Agreement on Mactung Project
A definitive Asset Purchase Agreement has been signed with the Government of Northwest Territories to acquire a 100% interest in the 37.6 km² Mactung tungsten project on the Yukon–Northwest Territories border for C$15,000,000, comprising $1,500,000 already paid, $3,500,000 within 18 months of closing, $5,000,000 on announcing intent to build a mine at Mactung or Macmillan Pass, and $5,000,000 on a
AcquisitionFireweed Reports New Mineralization At MacMillan Pass, Update For Mactung And Gayna River
Drilling at the Macmillan Pass zinc-lead-silver project in Yukon has intersected massive pyrite-sphalerite-galena mineralization in holes NB22-001 and NB22-002 south of a fault at Boundary West, 120 m and 30 m laterally from hole NB21-002's intersection of 8.22% zinc, 0.71% lead and 53.6 g/t silver over 316-377 m, while hole NB22-008 encountered laminated zinc-lead mineralization from 41.89-42.89
Drill resultsFireweed Zinc Acquires Mactung Tungsten Project
A binding letter of intent has been signed with the Government of the Northwest Territories to acquire a 100% interest in the 37.6 km² Mactung Tungsten Project, straddling Yukon and the Northwest Territories adjacent to Fireweed's Macmillan Pass project, for C$15,000,000: $1,500,000 on signing, $3,500,000 within 18 months on a definitive agreement, and two $5,000,000 payments tied to mine construc