Key facts
| Company | E3 Lithium (TSXV: ETL) |
|---|---|
| Commodity | Gold |
| Location | Alberta, Canada |
| Stage | Pre-feasibility |
Economic studies
Pre-feasibility study
Jul 29, 2024- IRR
- 24.6%
- Payback
- 4 years
- Initial capex
- US$2465M
- Mine life
- 50 years
Figures as extracted from each study, in US dollars as the studies report them. Open the report before relying on one.
News releases11 on file
E3 Lithium Provides Status Update on Clearwater Project
Phase 2 of the Clearwater Project Demonstration Facility in Alberta is nearing completion, with operations shifting to lithium carbonate production as Phase 3 ramps up and an expanded commercial-scaled DLE column is deployed, with operations expected to run through 2027. Natural Resources Canada's Global Partnerships Initiative is providing up to $36.5 million in non-repayable funding for Phase 3
CorporateE3 LITHIUM ANNOUNCES UPSIZE OF BEST EFFORTS EQUITY FINANCING TO $10 MILLION
A previously announced best efforts public offering has been upsized from approximately C$8.5 million to approximately C$10 million, comprising 11,115,000 units at C$0.90 per unit, each unit including one common share and one warrant exercisable at C$1.10 for 36 months. Agents ATB Cormark Capital Markets and Canaccord Genuity hold a 30-day over-allotment option for up to 1,667,250 additional units
FinancingE3 LITHIUM ANNOUNCES $8.5 MILLION BEST EFFORTS EQUITY FINANCING
A best efforts public offering of 9,450,000 units at C$0.90 per unit for gross proceeds of approximately C$8.5 million has been agreed with ATB Cormark Capital Markets and Canaccord Genuity Corp. as co-lead agents. Each unit comprises one common share and one warrant exercisable at C$1.10 for 36 months, with a 15% over-allotment option exercisable for 30 days. Closing is expected on or about Septe
FinancingE3 Lithium's Clearwater Project Selected for the Canada Investment Summit Prospectus; Company Establishes Strategic Advisory Group
E3 Lithium's Clearwater Project in Alberta's Bashaw District has been selected for inclusion in the Canada Investment Summit Prospectus, a shortlist of Canadian projects presented to global institutional investors at the Summit hosted by Prime Minister Mark Carney in partnership with CPP Investments and PSP Investments in Toronto on September 14 and 15, 2026, with an objective of attracting up to
CorporateE3 Lithium Advances European Market Strategy Through Collaboration Agreement with Tees Valley Lithium
A non-binding Collaboration Agreement has been signed with Tees Valley Lithium Ltd., a wholly owned subsidiary of Alkemy Capital Investments plc, under which E3 could use TVL's UK refinery to convert lithium carbonate from the Clearwater Project in Alberta into battery-grade lithium hydroxide for European customers. The agreement contemplates up to 50,000 tonnes of lithium hydroxide over an initia
CorporateE3 Lithium Successfully Commissions Phase 2 of its Demonstration Facility
Phase 2 of the Clearwater Project Demonstration Facility in Alberta has been commissioned, with a reservoir production test underway. Brine produced from the production test assayed 75.8 mg/L lithium, verified by an independent third-party laboratory, and the well-pair maintained a targeted flowrate of 1,400 m³/day at steady state via an electrical submersible pump. Data will feed the Reservoir De
CorporateE3 Lithium Welcomes Tom Gear as Chief Operating Officer; Kevin Carroll to Retire
Tom Gear has been appointed Chief Operating Officer of E3 Lithium, effective June 8, 2026. Chief Development Officer Kevin Carroll is retiring, with his last day on June 12, 2026, and will remain as an advisor during a transition period. Gear was previously Senior Vice President Oilsands at MEG Energy and spent 24 years at Suncor and legacy Petro-Canada. E3 is advancing the Clearwater Project in A
ManagementE3 Lithium Releases Q1 2026 Results and Continues Advancement Toward Commercialization
Unaudited Q1 2026 financial statements and MD&A for the three months ended March 31, 2026 were filed on SEDAR+. During the quarter, E3 delivered battery-grade lithium carbonate to offtake and strategic partners, submitted a Directive 056 facility licence application to the Alberta Energy Regulator for the Clearwater Project's Central Processing Facility, and entered a $2.0 million operating loan f
CorporateE3 Lithium Set to Begin Operations for Phase 2 of the Demonstration Facility
Well development and pump installation are complete at E3 Lithium's Demonstration Facility in South-Central Alberta, with Phase 2 operations set to begin once the Directive 51 licence is received. Phase 2 will run 8-12 weeks, comprising a Leduc Reservoir production test and brine and gas chemistry collection to supply remaining technical data for the Clearwater Project Feasibility Study. Phase 3,
CorporateE3 Lithium Files 2025 Year-End Financial Results and Disclosure Documents
E3 Lithium has filed its consolidated financial statements for the year ended December 31, 2025, along with its Management's Discussion and Analysis and Annual Information Form. The documents are available on SEDAR+ and the company's website. E3 holds 21.2 million tonnes of lithium carbonate equivalent in Measured and Indicated resources plus 0.3 Mt LCE Inferred in Alberta, with the Clearwater Pre
CorporateE3 Lithium Submits Directive 056 Facility Licence Application as Next Step in Clearwater Project Development
An application under Directive 056 for a facility licence for the Clearwater Project's Central Processing Facility has been submitted to the Alberta Energy Regulator, following the Environmental Protection and Enhancement Act application filed in late 2025. Both permits are required to build and operate the facility, with further applications for wells, pipeline and scheme approval planned through
Corporate